Street lighting projects
17th September 2009 Contract award North Ayrshire Council,
Dreghorn. The Courts Phase 1 Deteriorated Column Replacements. Supply and installation of 112 New Street lighting columns, trenching on the public pavement and carriageway 2,797 metres and installation of 2,804 meters of SWA cable, final electrical connections completed by our electricians.
August 2009 Contract award East Ayrshire Council
Portland Brae, Hurlford Lighting Improvement. Supply and installation of 9 New Street lighting columns and supply and installation of 330 metres of SWA cable, final connection and testing completed by East Ayrshire council.
July 2009 Contract award East Ayrshire Council
Campsie Road Kilmarnock, Lighting Improvement. Supply and installation of 33 new Street lighting columns, trenching on the public pavement 1,030 metres and installation of 1,230 meters of SWA cable, final electrical connections completed by East Ayrshire Council.
June 2009 Contract award East Ayrshire Council
Blair Crescent area Galston, Lighting Improvement. Supply and installation of 22 new Street lighting columns, trenching on the public pavement 814 metres and installation of 800 meters of SWA cable, final electrical connections completed by East Ayrshire Council.
June 2009 Contract award East Ayrshire Council,
Keir Hardie Hill, Cumnock Lighting Improvement. Supply and installation of 26 new Street lighting columns, trenching on the public pavement 840 metres and installation of 920 meters of SWA cable, final electrical connections completed by East Ayrshire Council.
June 2009 Contract award South Ayrshire Council
Girvan, Motehill Road Street Lighting replacement. Supply and installation of 179 New Street lighting columns, trenching on the public pavement 5,470 metres and 800 metres in carriageway and installation of 7,950m of SWA cable with final connection and testing completed by our electricians
December 2008 Contract award North Ayrshire Council,
Kilbirnie, Loadingbank area, Deteriorated column replacement. Supply and installation of 125 new Street lighting columns, trenching on the public pavement 3,000 metres and installation of 3,550 of SWA cable, final connection and testing completed by our electricians
June 2008 Contract award Interserve Project Services Ltd,
PPP Project, Victoria Hospital Kirkcaldy column replacement contract. Supply and installation of 60 new Street lighting columns, trenching on the public pavement 2,600 metres and installation of 2,884 metres of SWA cable, final connection and testing completed by our electricians